Hollandse Kust Noord Offshore Wind Farm

52°42′54″N 4°15′04″E / 52.7151°N 4.251°E / 52.7151; 4.251StatusOperationalConstruction began
  • 15 October 2022
Commission date
  • 20 December 2023
Owner(s)
  • Eneco
  • Shell plc
Wind farm Type
  • Offshore
Distance from shore
  • 18.5 km (11.5 mi)
Hub height
  • 125.5 m (412 ft)
Rotor diameter
  • 200 m (660 ft)
Rated wind speed
  • 9.57 m/s (31.4 ft/s)
Site area
  • 92 km2 (36 sq mi)
Power generation Units planned69 × 11 MWNameplate capacity
  • 759 MW
External linksWebsitewww.crosswindhkn.nl
[edit on Wikidata]
Map
Wind farm layout

Hollandse Kust Noord Wind Farm (officially Hollandse Kust (Noord) Wind Farm Zone) is an offshore wind farm in the Dutch part of the North sea.[1] The wind farm zone consists of a single site. The farm will consist of 69 wind turbines with a capacity of 11 MW each and will have a total output of 759 MW.

Construction on the farm started in October 2022. [2] The last of the monopile foundation was installed in February 2023[3] and the first wind turbine was installed in April 2023.[4] The farm is expected to be fully operational by the end of 2023.

See also

References

  1. ^ "Hollandse Kust (noord) wind farm zone including Prinses Amalia Wind Farm (PAWF)". Noordzeeloket UK. Retrieved 2023-06-30.
  2. ^ "Construction offshore wind farm Hollandse Kust Noord commences". Crosswind Hollandse Kust Noord (in Dutch). Retrieved 2023-06-30.
  3. ^ "Final monopile installed at Hollandse Kust Noord offshore wind farm". Crosswind Hollandse Kust Noord (in Dutch). Retrieved 2023-06-30.
  4. ^ "First turbine rises at Hollandse Kust Noord offshore wind park". Crosswind Hollandse Kust Noord (in Dutch). Retrieved 2023-06-30.
  • v
  • t
  • e
Wind power
Wind powerWind farmsWind turbinesWind power industryManufacturersConcepts
  • icon Wind power portal
  • Category
  • Commons
  • Additional portals:
  • Renewable energy
  • Energy